The Sewer Use and Drainage Permits (SUDP) division is housed
                                               within Development Engineering Services with DOTI. For adap-
                                               tive reuse projects, applicants typically interact with this division
                                               regarding grease interceptors which require a plumbing and an
                                               SUDP review. New grease interceptors are typically needed when
                                               a restaurant or commercial kitchen changes the type of cuisine
                                               served, increases seating capacity or changes the cooking applianc-
                                               es used.


                                               Each review group sets and charges their own fees individually.

                                               Typical CPD Issues Encountered in Adaptive Reuse
                                               With adaptive reuse applications, a series of reoccurring issues
                                               were raised in conversations with City staff and those in the devel-
                                               opment community. These issues are described below.

                                               i.  Zoning Code Requirements
                                               For adaptive reuse applicants, zoning code requirements pose one
                                               of the biggest hurdles to completing a successful project and open-
                                               ing a small business in an adaptively reused space. While every
                                               site and building present unique challenges, a series of common
                                               zoning code-related challenges were raised by many who have
                                               worked on an adaptive reuse project in the past. The following
                                               items describe components of the zoning code that often become
                                               obstacles for completing an adaptive reuse project.

                                               a.  Provide flexibility to adaptive reuse projects in Main
                                                  Street Zone Districts
                                               The majority of properties along the East Colfax corridor are in
                                               the Main Street Zone District, although the specifications may
                                               change. While the Zone District is well-intentioned to create a
                                               corridor that is pedestrian-scaled, safe, has active street edges, and
                                               is walkable, it often creates challenges for adaptive reuse projects.
                                               These projects are not recognized in the general purpose state-
                                               ment of the zone district, but instead, the focus remains on en-
                                               suring new development positively contributes to the established
                                               character of the corridor. Abiding by the standards established
                                               for new development, including the build-to requirements and
                                               parking standards, can be a challenge for adaptive reuse project
                                               applicants.

                                               b.  Setbacks and Build-To Requirements
                                               Lots are often small along Colfax, so any requirements that eat
                                               into the developable area make it increasingly difficult for a proj-
                                               ect to pencil. Setbacks for properties along the Colfax corridor
                                               are most often 0’. Build-to requirements, therefore, are what
                                               applicants must follow. Front and rear build-to requirements were
                                               frequently raised as problematic for some lots, especially those that


              22                                                                             City of Denver, CO
   21   22   23   24   25   26   27   28   29   30   31