Typical Fire Department Issues Encountered in Adaptive
                                               Reuse
                                               Fire Department staff highlight key issues that often arise during
                                               permit review for adaptive reuse projects.

                                               i.  Egress
                                               FD inspectors note for some adaptive reuse projects, meeting
                                               emergency egress standards often becomes an issue. Exits may not
                                               be adequately separated and existing doorways may not be wide
                                               enough. In these cases, there can be requirements that are techni-
                                               cally infeasible requirements for the project. While a compromise
                                               (explained more below in “Current Flexibility”) must be met in
                                               order to grant occupancy, ensuring life safety is the key goal of the
                                               FD review.

                                               ii.  Sprinklers
                                               The cost of installing commercial grade sprinkler systems is higher
                                               than many adaptive reuse applicants realize prior to beginning
                                               a project. In some cases, the Fire Department can organize the
                                               building spaces into zones that reduce the need for sprinklers.
                                               Some other communities with adaptive reuse programs allow proj-
                                               ects to utilize residential grade sprinklers in order to cut costs.

                                               iii.  Exit location/separation distance/stairs
                                               Meeting emergency exit requirements also is an issue that arises.
                                               For example, the exits may not meet the minimum separation
                                               requirement. Some flexibility is available applying this standard
                                               when exit routes are established that make best use of existing ex-
                                               its. Other code requirements for the rise and run of stairs and the
                                               width of door openings can be issues. Some flexibility is available
                                               for these as well. Each of these situations is addressed individually,
                                               as several variables influence the ability to apply lesser standards.
                                               As a result, applicants may not know the range of flexibility that
                                               may be available to them.


                                               Current Flexibility in the Fire Department
                                               Ensuring the safety of lives and properties is, of course, key. Much
                                               of what is considered appropriate will be based on the proposed
                                               change of use and occupancy. While some flexibility is available,
                                               the key goals of life and safety must not be compromised. Staff
                                               note that when an adaptive reuse project does not meet the cur-
                                               rent Fire Code, they work closely with the Building Department
                                               and try to get the project as close as possible to meeting code. An
                                               Administration Modification process is used in some cases as well,
                                               in which the FD and the architectural/structural team (part of
                                               development services) meet to discuss complicated aspects of a
                                               project. The objective is to find a means of granting a certificate
                                               of occupancy without using the board of appeals process.